With production machinery booked for delivery, discovering that your compressor cannot run at the new factory puts the restart date at risk. Before relocating your air compressor, check the equipment’s condition, the new installation requirements and who will authorise its return to service.

At J Ll Leach, Atlas Copco authorised distributor in the West Midlands, we approach this through compressed air installation and project planning. Moving the machine is one part of the job. The receiver, dryer, electrical supply, pipework and examination records need their own checks.

Your air compressor relocation checklist should separate decisions made before shutdown from moving-day work and recommissioning.

Before the Move: Build an Equipment Record

Start while the existing system is still running. Once it is disconnected, useful evidence about pressure, temperature and production demand becomes harder to collect.

Create a record for every item you intend to reuse:

Keep these records together and give the relevant contractors access. Label equipment consistently across drawings, photographs and the move schedule.

Capture a Performance Baseline

Record pressure at the compressor and critical production points during representative demand. Note which machines are operating, whether the compressor is loaded or unloaded, and any existing pressure complaints.

For a metalworking business leaving Tyseley, the important comparison is the air available when production equipment runs together. A quiet-period pressure reading tells you little about that condition.

We recommend recording known faults before shutdown. Otherwise, an existing leak or dryer problem can become confused with damage caused during transport.

Use this baseline when accepting the new installation. It gives your team something measurable to compare against.

Is the Existing Compressor Worth Reusing?

A premises move is a useful point to review the equipment. It does not automatically justify replacing a serviceable compressor.

Compare the installed cost of reuse with replacement. Include repairs, transport, reconnection, treatment equipment and temporary production cover.

Review Condition Before Booking Transport

Arrange a condition assessment before committing to the move. Give the engineer the service records and identify anything operators have noticed, including unusual noise, oil leaks or repeated temperature trips.

The assessment should address the compressor and its supporting equipment. A reliable compressor paired with an unsuitable dryer still leaves a problem at the new site.

Use age and running hours alongside inspection findings. Neither provides a universal retirement point. Parts availability, repair requirements and suitability for the new duty also affect the decision.

Our Birmingham air compressor maintenance checklist can help organise maintenance records before that assessment.

Match Reuse to the New Production Demand

Confirm whether production demand will change. Additional machines, longer shifts or different processes can alter the required flow, pressure and air quality.

Compare free air delivery, meaning the compressor’s delivered airflow expressed at reference inlet conditions, at the specified pressure. Motor power alone is not enough to establish suitability.

For the wider sizing method, see our technical guide to sizing air compressors.

Use the assessment to compare practical options:

OptionWhen It Deserves ConsiderationWhat Needs Resolving
Reuse the existing systemIts condition and performance suit the new duty.Installation changes and outstanding maintenance.
Reuse with targeted replacementThe compressor suits demand, but supporting equipment does not.Dryer, filter, receiver or control requirements.
Replace the compressorCondition, repair cost or demand makes reuse unattractive.Verified performance and the complete installed cost.
Use temporary hire during changeoverProduction must continue while permanent equipment is unavailable.Capacity, air quality, connections and examination records.

An older machine with documented maintenance may remain a sensible choice. A newer machine with unresolved faults may not. That decision stays open until the equipment and new duty have been assessed.

Will the Equipment Fit and Operate at the New Site?

Survey both buildings. The removal route can be more difficult than the delivery route, especially where production equipment has been added around the compressor.

Check the new location against the exact installation instructions. Avoid using a generic clearance or weight taken from a similar machine.

Measure the Entire Handling Route

Record door openings, corridor widths, overhead restrictions, thresholds, gradients and turning space. Include loading areas and the route from the vehicle to the final position.

Obtain the equipment’s documented mass and approved handling points. The lifting contractor must assess the proposed equipment for the load and handling arrangement.

Lifting operations fall under the Lifting Operations and Lifting Equipment Regulations 1998. They must be properly planned by a competent person, appropriately supervised and carried out safely, as explained in HSE’s lifting guidance (hse.gov.uk).

If the proposed position involves a mezzanine, raised platform or uncertain floor construction, resolve its suitability before booking delivery. A successful unloading operation does not establish that the final position can support the equipment.

Preserve Cooling and Maintenance Access

Check the manufacturer’s required service clearances and cooling arrangements. Allow access for opening panels, servicing the dryer and removing components.

Confirm how cooling air enters and heated air leaves. Include duct connections and any building alterations needed before the compressor arrives.

Atlas Copco identifies ventilation, condensate drainage and service access among the factors affecting installation suitability in its compressor placement guidance (atlascopco.com).

A position that fits the cabinet can still make maintenance difficult. Check access with doors and panels open, rather than measuring the closed machine alone.

Agree the Pipework and Treatment Arrangement

Draw the proposed system from compressor outlet to production connections. Show the receiver, dryer, filters, isolation points, drains and any temporary supply connection.

Specify pipework and fittings suitable for compressed air service and the installation’s pressure, temperature and flow requirements. Assess the condition and suitability of components proposed for reuse.

Confirm the air quality needed by each process. Do not assume the old treatment arrangement remains suitable because the compressor is unchanged.

Where a project includes medical applications, our page on air compressors in the medical industry provides relevant context. Such applications need their own specification and acceptance requirements before connection.

Which Compliance Checks Must Be Arranged Before Shutdown?

In Great Britain, the relocation plan must address the applicable pressure-system, work-equipment and electrical safety duties.

These checks have different purposes. A maintenance visit does not replace a statutory pressure-system examination. An electrical test does not establish that the assembled compressed air system meets its operating requirements.

Review the Pressure-System Examination Requirements

The Pressure Systems Safety Regulations 2000 (legislation.gov.uk) govern relevant pressure systems used at work. For qualifying equipment, a suitable Written Scheme of Examination and the required examination must be in place before use, as set out in HSE’s PSSR guidance (hse.gov.uk).

The scheme identifies the parts requiring examination and specifies its nature and frequency. It must be suitable for the system’s current conditions of use.

Give the competent person the proposed layout, equipment records and existing reports before the move. Ask them to determine any changes to the scheme and examinations needed before restart.

A relocation does not automatically erase every existing record. Equally, paperwork describing the old installation is not sufficient evidence for a changed arrangement. The scheme’s suitability must be reviewed, with changes made where required by the competent person. This follows HSE’s approved code of practice (hse.gov.uk).

Arrange Inspection After Reassembly

The Provision and Use of Work Equipment Regulations 1998, or PUWER, also apply.

Where equipment safety depends on installation conditions, inspection is required after installation and before first use, including after reassembly at a new location. HSE’s work-equipment inspection guidance (hse.gov.uk) explains this requirement.

Agree the inspection scope through risk assessment and manufacturer instructions. It should address the safety-related features of the reassembled equipment.

Record the result and resolve defects affecting safe operation before use. Put this inspection into the programme alongside the pressure-system and electrical checks, with responsibility assigned.

Confirm the Electrical Design and Applicable Standard

Electrical work must meet the Electricity at Work Regulations 1989. Appoint an electrical contractor competent for the equipment and installation involved.

Give them the compressor’s electrical data and installation instructions. Ask them to assess supply capacity, voltage, phase arrangement, cable route, starting requirements, protective devices, earthing and isolation.

BS 7671 is the national standard for electrical installations. Specify the edition applicable to the work and confirm the project basis using the IET edition checker (electrical.theiet.org).

A three-phase supply at the new factory does not, by itself, establish that the compressor can be connected safely.

Set the Changeover Sequence Around Production

Build the programme backwards from the first production shift requiring compressed air. Include installation, inspections, testing and time to resolve defects.

Avoid treating the transport booking as the main completion date. Equipment delivered to site may still need several dependencies resolved before it can operate.

Assign Each Interface to a Named Owner

Use one project schedule covering the factory team, electrical contractor, installation engineers, lifting contractor and pressure-system competent person.

Identify who will confirm each prerequisite:

Keep the old compressor operating until the agreed shutdown point. If both factories need air during an overlap, identify that requirement before disconnecting equipment.

A short move between Aston and another Birmingham industrial site can still involve separate production schedules. Distance does not remove the need for a coordinated changeover.

Specify Temporary Hire as an Installation

We provide air compressor hire, but temporary cover still needs a defined operating requirement. Specify flow, pressure, air quality, connections and the period when air must be available.

Operating a hired installed compressor without the required statutory examination can leave your company criminally liable (legislation.gov.uk) for breaching PSSR 2000. For qualifying hired pressure equipment, obtain the applicable Written Scheme of Examination and current statutory examination documentation. Check equipment identification and outstanding restrictions before use.

Responsibility also depends on whether the system is mobile or installed. Where applicable, Schedule 2 permits specified duties for hired installed systems to be assumed by the supplier through a written agreement. Confirm that arrangement using the PSSR hire provisions (hse.gov.uk).

Do not assume delivery of a hired compressor settles the safety of its connections to your factory.

Moving Day: Decommission Before Disconnecting

Electrical isolation and pressure release must be completed before connections are disturbed.

Use a task-specific method statement based on the manufacturer’s instructions. Electrical work, pressure-system work and lifting should be undertaken by people competent for their assigned tasks.

Shut Down and Secure All Energy Sources

Follow the normal shutdown procedure and allow the equipment to cool as required. Identify every source capable of energising or pressurising the equipment.

Securely isolate electrical supplies and prevent reconnection. Where work involves exposed conductors, the electrical worker must prove them dead using suitable test equipment.

Isolate the compressor from the connected air system. Release stored pressure through the prescribed procedure and verify the relevant parts are safe before opening connections.

HSE explains that electrical equipment should be securely isolated and checked to be dead before work begins. Follow the equipment instructions and site rules, as described in its safe-isolation guidance (hse.gov.uk).

Account for separate dryer supplies, remote controls and connections to other compressors. Pressurised downstream pipework must remain controlled throughout the work.

Protect the Equipment for Transport

Label connections before removal and photograph anything needed for reassembly. Protect disconnected openings against dirt and water.

Follow the manufacturer’s transport instructions for handling orientation, restraints, fluids and any shipping supports. Do not drain lubricating oil or remove internal components simply because another machine required it.

Keep removed guards, brackets and accessories identified with their equipment. Store documentation separately so it remains available during installation.

The lifting contractor should control loading and unloading under the agreed plan. Keep other workers clear of the handling area.

Inspect the equipment after delivery and record visible damage before installation continues. If its condition differs from the pre-move record, resolve the discrepancy before commissioning.

Recommissioning: What Must Be Proven Before Production Restarts?

Recommissioning should follow the model-specific instructions and the agreed acceptance plan. It covers the compressor and the assembled system supplying production.

Prepare that plan before the move. It should identify the required pressure, airflow, air quality and safety checks, with a person responsible for accepting each result.

Complete Mechanical and Electrical Checks

The installation engineer should confirm that the equipment is positioned and assembled correctly. Check connections, supports, guards, fluid levels, cooling provisions and drains.

Complete the specified inspection and testing of new or altered electrical work. Retain the relevant certificates and test records.

For three-phase equipment, verify supply phase sequence and any required motor or fan rotation checks using the manufacturer’s commissioning procedure. There is no universal rotation direction or safe jog duration for every compressor.

Atlas Copco provides model-specific installation and operating instructions through its technical documentation service (atlascopco.com).

Do not infer correct operation from familiar cable colours or the previous installation. Any discrepancy must be resolved before proceeding with the manufacturer’s start-up sequence.

Confirm Pressure-System Readiness

Check that the agreed pressure-system review, scheme changes and examinations have been completed. Address restrictions or defects identified by the competent person.

Have protective devices and operating settings checked by the appropriate competent personnel. Do not increase pressure settings to compensate for an installation problem.

Complete any specified integrity or leak testing using the agreed procedure. An improvised compressed-air pressure test can introduce hazards and is not a substitute for an approved method.

Keep the installation inspection, statutory examination and commissioning records distinguishable. Each provides different evidence.

Test the System Under Representative Demand

Follow the prescribed initial start-up sequence, then introduce production demand in a controlled way.

Record pressure at the compressor and critical use points. Observe temperature, alarms, loading behaviour and the performance of the dryer and drains.

Compare the results with the pre-move baseline and the new specification. If pressure deteriorates at a production connection, investigate the distribution arrangement before accepting the system.

Confirm air quality using the agreed testing where the process requires it. A normal pressure reading cannot establish dryness or cleanliness.

Test the combinations of machinery expected during production. A short run with little demand leaves the main operating question unanswered.

Hand Over the Operating Records

Before releasing the system, identify the person responsible for operation and maintenance. Give them the updated layout, instructions, certificates, examination records and commissioning results.

Record unresolved items and whether they prevent use. Allocate corrective work with clear ownership.

Brief operators on the new isolation points, alarms, drains and shutdown procedure. Set the first operating review for a representative shift so the installation can be checked under normal conditions.

Information Needed for an Installation Assessment

Generic guidance cannot determine whether your existing equipment suits the new factory. That requires the condition records, demand requirements and site details to be assessed together.

Our air compressor installation work covers that assessment and the installation project itself. Electrical and statutory examination responsibilities should be agreed within the project scope.

For useful project planning, prepare:

With those inputs, J Ll Leach can assess the compressed air installation requirements and identify equipment proposed for reuse. Your move programme can then allow for the work needed before the first production shift.